Module 11
  Spring 2010 Closure
  Compiled by Greg Kinney
  “MUDDIEST ITEMS” in this module:
  Question:
  The least clear thing I learned from this module was regarding  meetings on Page 505.  The fifth bullet  states “…do not report votes on controversial matters.”  It seems you would always want to report  votes on controversial matters to have record of staff/manager/agency  opinion.  If this information does not  make it on record, then there’s no background to the issue as to why the  decision was made the way it was.  
  Answer:
  I think that the record needs to reflect the substance of the  issue, some salient points that were considered, and the resolution, if there  was one.  (If there wasn’t, the record  should reflect accurately what the viewpoints were.)  But I agree that if it came down to a vote,  reporting of a vote is only going to create lots of questions – such as who  voted which way.  It also sows the seeds  of future controversy.  Bottom line,  there are ways to report accurately on a controversial issue without fanning  the flames, and reporting votes (whether by name or just by aggregate numbers)  doesn’t achieve that end.
Question:
  The muddiest thing from this chapter were some of the  calculations, not necessarily the math itself but what information to use for  what part of certain equations.  It seems  someone subjective as to what information can be used and what costs count for  certain parts of the equation.  Maybe I’m  just used to hard and fast numbers.  
  Answer:
  There is some fuzz on the numbers, particularly when you get  into estimating % complete.  It’s really  hard to estimate in certain kinds of projects.   So this is kind of a black art.   It’s easiest when you get into work that has a predefined schedule of  values, and completion of one activity has a defined earned value associated  with it based on the bid.  Even then,  updating the estimate requires a guess at % complete for the task(s) in  progress.
  Question:
  The muddiest item in this module is that since we can  calculate (estimate) the CV and SV, especially the SV, we will know the project  proceeded is behind/delay or ahead of the schedule. Why should we need to know  the TV?  
  Answer:
  Notwithstanding the fact that SV stands for schedule variance, it  really doesn’t give you a projection of how many days or weeks we are away from  completion.  It is actually just the  difference between how much value was earned vs. how much value was planned to  be earned as of right now.  The time  variance is the difference in the time scheduled for work to be performed vs.  how long it actually took.  In my  experience, I never hear people use the term “time variance” but they always  talk about how far behind schedule the project is.  So, even if they aren’t formally calculating  time variance, in fact that is the thing that people are discussing and  relating to.
Question:
  The muddiest part the websites first comments about the  monitoring and controlling cycle. I thought from reading that, there was some  set of standardized rules that could be applied to find the best monitoring and  controlling system. But it seems that the best system is whatever gives the PM  the reports consistent with the project objectives.  
  Answer:
  I agree.  A one size  fits all approach won’t work well; it has to be customized.
Question:
  If  I have to pick one “muddy” item, it would be the definition of “Software” in  the Glossary at the end of the chapter:   “The instructions for running a computer.”  I always thought that software was a program  or application that was run on a computer… not an instruction booklet  (sarcastic).